AIC Mines (ASX: A1M), a copper producer with a market capitalisation of about $552 million, will drill about 30,000 metres at Mt Cuthbert in northwest Queensland during 2027 to test the depth extensions of historic hits including 13.4 metres at 4.5% copper at Crusader.

The rigs arrive towards the end of the March 2027 quarter, after the wet season, and the shares traded at $0.560 on 27 November, 2.75% above the $0.545 price at the announcement’s release on 25 November.

The prize is a resource of 18.67 million tonnes grading 1.3% copper for 246,000 tonnes of contained copper across five deposits, effective 1 May 2026.

The historic sulphide hits the program will chase run well above that average: 56 metres at 1.9% copper from 56 metres at Kalkadoon (hole 15MC003DD), 19 metres at 2.2% copper from 126 metres at Mt Cuthbert (21MC011RC), and 18.6 metres at 2.8% copper from 229.7 metres at Crusader (18CRU026OHDD). Every one of those results was previously released, in September 2026, and the November announcement reported no new assays.

The case for drilling deeper is written in the historic hole count. Mt Cuthbert’s resource rests on 949 holes for 76,031 metres drilled between 1964 and 2024, yet the average resource hole reached only 73 metres.

Only 85 holes went below 200 metres and only 25 went deeper than 350 metres, so the depth of the deposits is defined by the limit of drilling rather than the limit of mineralisation, the company says.

Earlier drilling largely targeted shallow oxide mineralisation, the near-surface copper that fed heap leach and SXEW processing, while the sulphide copper below it went largely untested.

Bar chart of AIC Mines’ planned 2027 drilling at Mt Cuthbert by target: Mt Cuthbert-Kalkadoon 12,000 to 13,000 metres, Crusader 11,000 to 12,000 metres, Mt Watson 2,000 to 3,000 metres, and early-stage prospects about 3,000 metres, for a total of about 30,000 metres. Source: AIC Mines ASX announcement, 25 November 2026.

The first phase covers about 27,000 metres across the three main deposits, plus about 3,000 metres for early-stage prospects and possible new discoveries. Mt Cuthbert-Kalkadoon takes 12,000 to 13,000 metres, Crusader 11,000 to 12,000 metres and Mt Watson 2,000 to 3,000 metres.

The $70 million placement completed on 11 November funds a planned two-year exploration and resource definition program at Mt Cuthbert, along with transaction costs, environmental baseline studies and development studies.

AIC Mines completed the acquisition of Mt Cuthbert on 11 November through its purchase of Materra Metals, issuing 88,050,315 shares to Hawke’s Point Resource Finance and its affiliates for the $70 million.

The project covers about 2,400 square kilometres across 21 mining leases and 32 exploration permits, about 100 kilometres northwest of Cloncurry and 150 kilometres northwest of AIC Mines’ Eloise copper mine. It also holds an 8,000-tonne-a-year SXEW processing plant, solvent extraction and electrowinning, built for the shallow oxide ore earlier owners mined.

Managing director Clint Donkin said the project offered the chance to investigate mineralisation beneath previously mined and explored areas. “Mt Cuthbert has seen very little drilling below the shallow oxide and transitional zones targeted by previous owners,” he said. “The limited deeper drilling that has been completed is very encouraging.”

“Our 2027 drilling program is designed to systematically test that depth potential across the major deposits,” Donkin said. “With the acquisition now complete and the drilling program funded, our immediate objective is to determine how much larger the Mt Cuthbert resource could become ahead of development studies.”

Where will the rigs go first?

At Mt Cuthbert-Kalkadoon, drilling targets high-grade shoots below 250 metres and a 500-metre gap between the two deposits that has never been drilled. Only 19 holes have gone below 200 metres at the main deposit, and all of them intersected sulphide mineralisation. The deposit holds 5.88 million tonnes at 1.7% copper for 98,700 tonnes of contained copper, the richest of the three main deposits on grade.

At Crusader, drilling tests depth extensions below 350 metres and strike towards the Sparklet prospect. Mineralisation there runs over 1,500 metres of strike to 350 metres depth and remains open in both directions. Crusader holds 5.97 million tonnes at 1.6% copper for 93,400 tonnes.

Bar chart of historic drilling depth at Mt Cuthbert: 864 of 949 holes stopped at 200 metres or less, 60 holes went between 200 and 350 metres, and only 25 holes went deeper than 350 metres. The average resource hole reached only 73 metres. Source: AIC Mines ASX announcement, 25 November 2026.

At Mt Watson, 2,000 to 3,000 metres targets plunging high-grade sulphide shoots below about 100 metres. Historic drilling tested 1,600 metres of strike largely to 100 metres depth, ending in the transitional zone above the sulphides, with only seven holes reaching about 300 metres.

Mt Watson holds 5.73 million tonnes at 0.7% copper for 40,300 tonnes, the lowest grade of the three main deposits. The remaining resource sits at Warwick Castle, 110,000 tonnes at 2.3% copper, and Leichhardt, 1 million tonnes at 1.1% copper.

What would success look like?

Success, in the company’s words, is a bigger resource ahead of development studies. Chairman Aaron Colleran told shareholders at the annual general meeting on 25 November that the immediate focus is to determine the best way to develop Mt Cuthbert as a standalone operation. The project already sits inside a producing business: Jericho entered production in September, and construction of the Eloise processing plant expansion was completed earlier in November.

The caution sits in the announcement itself. References to exploration potential are conceptual, the company says, and it is uncertain whether further exploration will result in the determination of a mineral resource. The 2027 program is a test of that potential, not a promise of it.

The test comes when the rigs turn towards the end of the March 2027 quarter. If the deeper holes repeat the historic sulphide hits at Kalkadoon and Crusader, and if the 500-metre gap between Mt Cuthbert and Kalkadoon joins up, the resource has room to grow. Assays from the first phase will show whether the ground below 200 metres holds the copper the shallow drilling never reached.