A deal by 31 March 2027 would let crews return to underground work at Oyu Tolgoi that two disputed licences have blocked. Entrée Resources (TSX: ETG) reached that target with the Mongolian government for the Shivee Tolgoi and Javkhlant licences, which cover ground at the Hugo North Extension copper-gold deposit.

The framework was agreed at meetings on 9 and 10 November between Entrée and a reconstituted Mongolian government working group, the company said on 27 November. The two sides will make reasonable efforts to resolve the outstanding matters in the first quarter of 2027, and they can extend the talks by mutual consent if they cannot reach agreement in that time.

Resolving the dispute would unblock the transfer of the Shivee Tolgoi and Javkhlant licences from Entrée’s Mongolian subsidiary, Entrée LLC, to mine operator Oyu Tolgoi LLC. That transfer is required before crews can resume Lift 1 Panel 1 lateral development on the Shivee Tolgoi licence, work that has been paused since 6 June 2025.

Entrée holds a 20% or 30% carried interest in the Entrée/Oyu Tolgoi joint venture, depending on the depth of mineralisation. Development on the joint venture ground cannot resume until Oyu Tolgoi LLC, the mine operator and Entrée’s partner, holds the licences itself. Mining elsewhere at Oyu Tolgoi has carried on in the meantime.

“The Company remains committed to working towards a constructive solution that serves the interests of all Oyu Tolgoi project stakeholders and enables OT LLC to resume Lift 1 underground development and extraction activities on the Shivee Tolgoi license area,” Entrée said in its 27 November release.

Entrée Resources (TSX: ETG)

The pause has already cost the project more than a year of Panel 1 development. Lateral work on the Shivee Tolgoi licence began in October 2024 in rock classified as waste, and about 230 equivalent metres had been completed, mostly on the return air level, by 30 May 2025, a week before Entrée announced the pause.

Under the 2025 Oyu Tolgoi mine plan, work in the Hugo North Extension deposit footprint had been conditionally scheduled to start in June 2025. Instead, the operator shifted its focus to Lift 1 Panel 2 South on its wholly owned Oyu Tolgoi mining licence to limit the operational and financial impact.

Entrée chief executive Chris Adams called resolving the dispute “a pivotal moment in Entrée’s 25-year history” in a shareholder letter on 28 September, Mining.com reported. Of the first underground level, Panel 1 will enter production last. Part of the panel lies on Shivee Tolgoi ground.

Mining.com reported that Friday trading in Toronto left Entrée valued at about C$486 million. The Vancouver-based company’s shares closed at C$2.19, up 7 Canadian cents, or 3.3%, on the day. Royal Gold holds about 23% of Entrée’s shares and Rio Tinto about 15%, according to Entrée.

The company is not short of cash while it waits. Entrée held US$2.5 million in cash at 30 September, then closed a C$36.2 million private placement on 4 November, issuing 12,485,300 units at C$2.90 each. A significant part of the raising went to a new strategic investor, an affiliate of the Tether group of companies. Entrée reported an operating loss of US$1.0 million for the third quarter.

The stake or the royalty

Mongolia must choose between two ways of taking its share from Entrée LLC, the subsidiary holding both licences: an equity stake of up to 34%, or royalty payments in its place. Mongolia’s Minerals Law allows the state to hold up to 34% of a private company exploiting a deposit of strategic importance, where proven reserves were determined without state budget funding, and Parliament may decide the state receives royalty payments in lieu of an equity interest.

The framework the two sides agreed expressly acknowledges that, under Article 8.1.7 of the Minerals Law, Mongolia’s Parliament has the authority to determine the state’s shareholding percentage and to decide whether it is replaced by a special royalty. Nothing in the framework prejudges the form, scope or structure of any arrangement, which remains subject to negotiation and all necessary approvals.

Entrée offered a royalty in March. On 25 March it delivered a non-binding proposal to the then head of the government working group, contemplating a negotiated royalty on the gross sales value of its share of concentrate in place of a 34% state equity stake. The company said it received no formal response and will prepare a revised proposal, in consultation with other stakeholders, for the reconstituted working group.

That working group was reconstituted on 2 October under an order of Mongolia’s prime minister and is led by the Minister of Justice and Internal Affairs. Mongolia’s state news agency Montsame reported on 26 November that the next round of talks is scheduled for January, and that the working group will put its proposed solution to Parliament for a final decision once negotiations are complete.

Parliament has already set the direction of travel. Resolution No. 120, approved on 26 December 2025, directs the government to ensure the people hold the majority of the benefits from exploitation on the licences and to establish conditions to avoid future financial or investment obligations that could reduce Mongolia’s share.

One administrative hurdle still stands in the way of the licence transfer itself. During the third quarter, Mongolia’s tax authority told Entrée LLC it could not issue tax payment certificates because the documents supporting the licence valuations were incomplete. The certificates must be submitted to Mongolia’s Mineral Resources and Petroleum Authority to register the transfer.

Rio Tinto (ASX: RIO)

For Rio Tinto, which owns 66% of Oyu Tolgoi LLC and manages the operation, the March target matters because Oyu Tolgoi is set to become the world’s fourth-largest copper mine by 2030. Mongolia owns the other 34% through Erdenes Oyu Tolgoi.

Oyu Tolgoi is expected to produce an average of around 500,000 tonnes of copper a year from 2028 to 2036 from the open pit and underground mine, Rio Tinto said. The ramp-up remains on track: copper production rose 29% in the year to date, with the operation running at an annualised rate of about 450,000 tonnes in the third quarter, driven by the Lift 1 underground ramp-up on the Oyu Tolgoi mining licence, higher grades and better recoveries.

While the Panel 1 transfer remains unresolved, the operator continues to advance Panels 0 and 2 North, followed by Panel 2 South, all on the Oyu Tolgoi mining licence. In the production sequence, Panel 1 comes after every other panel, including those on the Oyu Tolgoi licence alone.

Rio Tinto disclosed in October that Mongolia agreed in June 2026 to commence work on resolving the licence transfer for Panel 1. Entrée is also working with Oyu Tolgoi LLC towards a possible conversion of the joint venture agreement into a more effective agreement of equivalent economic value, subject to Toronto Stock Exchange acceptance.

Hugo North Extension drilling

Entrée’s partner drilled the seven underground infill holes at Hugo North Extension over 2023 to 2026, and Entrée published their assays with the framework announcement. The strongest result came from UGD1025A, where 125.31 metres from 362.69 metres downhole carried 1.28% copper with 0.27 grams of gold and 3.18 grams of silver per tonne, giving 1.45% copper equivalent.

Hole UGD918A returned 67.6 metres grading 0.95% copper, 0.203 grams of gold and 2.19 grams of silver per tonne from 438.6 metres, for 1.07% copper equivalent. Hole UGD918 cut 65.73 metres at 1.02% copper equivalent, and hole UGD757A returned 136.3 metres grading 0.76% copper for 0.84% copper equivalent.

The longest hole in the batch, UGD1053, ran 527.7 metres grading 0.47% copper for 0.51% copper equivalent, including 252 metres at 0.59% copper. It was drilled mainly for geotechnical purposes, parallel to the eastern edge of the deposit.

The intervals are downhole lengths, not true widths. For holes drilled across the mineralised trend, Entrée estimates true widths at 20% to 70% of the reported lengths. Copper equivalent is calculated under the formula in Entrée’s October 2021 technical report, using metal prices of US$3.08 a pound for copper, US$1,292 an ounce for gold and US$19 an ounce for silver, with recoveries of 82%, 73% and 78% respectively.

Bar chart of copper equivalent grades for the six mineralised Hugo North Extension holes reported on 27 November 2026: UGD1025A 1.45% over 125.31 metres, UGD918A 1.07% over 67.6 metres, UGD918 1.02% over 65.73 metres, UGD757A 0.84% over 136.3 metres, UGD1012A 0.84% over 8.9 metres, and UGD1053 0.51% over 527.7 metres. Source: Entrée Resources news release, 27 November 2026.

Regional drilling on the joint venture ground continued in 2026. Oyu Tolgoi LLC provided collar details for three regional holes, one at the Ulaan Khud South target on the Shivee Tolgoi licence and two at the Heruga West target on the Javkhlant licence, with assays pending. Eight condemnation holes totalling 4,500 metres were drilled to confirm ground earmarked for expanded tailings storage is sterile; five returned no significant results.

Entrée is targeting the first quarter of 2027 to complete an updated technical report on its joint venture interest. The report will draw on the new Hugo North resource model for Lifts 1 and 2 and on a revised Lift 1 mine plan and production schedule.

Timeline of the Entrée licence dispute: lateral development begins October 2024; work pauses 6 June 2025 after about 230 equivalent metres; royalty proposal delivered 25 March 2026; government working group reconstituted 2 October 2026; negotiation framework agreed 9 to 10 November 2026; next talks scheduled January 2027; resolution targeted by 31 March 2027. Source: Entrée Resources releases, 2025 to 2026.

The test now is whether the January talks produce a proposal Parliament can approve. The March target is a commitment to make reasonable efforts, not a deadline with a penalty, and the two sides can extend it by mutual consent. If they do reach terms, the licence transfer, the tax certificates and the Panel 1 restart follow in sequence. If they do not, the pause that began in June 2025 simply runs on, and Panel 1 stays the last panel into production.