QMines (ASX:QML) has reported its strongest pontoon drilling result yet beneath the historical Mt Chalmers open pit in Queensland, a 46.8-metre intersection grading 2.29 per cent copper and 1.03 grams per tonne gold from 42.2 metres downhole.
The company’s own sensitivity test barely moves it, and a redrill that missed the workings entirely ended in high-grade copper.
The hole, 26MCDD051, was drilled vertically from a floating pontoon on the pit lake between 16 and 25 September 2026. It passed through two levels of underground workings dating to 1944 before reaching the footwall stringer zone below them.
That is the complication. The 46.8-metre interval includes core loss, backfill and material recovered from inside the old workings, some of which may have been displaced during earlier mining rather than sitting where it formed. QMines has published the sensitivity test: zero-grade the three samples most likely to be fill, and the interval falls only slightly, to 2.25 per cent copper and 1.00 grams per tonne gold.
The intercepts
All intervals are downhole lengths. True widths have not been established.
| Hole | Interval | Copper | Gold | From |
|---|---|---|---|---|
| 26MCDD051 | 46.8m | 2.29% | 1.03g/t | 42.2m |
| incl. 26MCDD051 | 12.0m | 4.63% | 2.41g/t | 46.0m |
| incl. 26MCDD051 | 9.0m | 5.39% | 2.76g/t | 48.0m |
| incl. 26MCDD051 | 9.8m | 3.06% | 1.02g/t | 63.2m |
| 26MCDD054 | 8.05m | 2.07% | 2.11g/t | 65.55m |
| 26MCDD054RD | 7.0m | 2.61% | 0.88g/t | 50.0m |
| incl. 26MCDD054RD | 2.0m | 8.62% | 2.65g/t | 55.0m |
Individual one-metre assays in 26MCDD051 reached 15.7 per cent copper and 8.04 grams per tonne gold. The broader interval also carries 4.2 grams per tonne silver, giving 3.20 per cent copper equivalent, calculated from spot prices on 11 September 2026 and the pre-feasibility study’s life-of-mine recoveries.
Drilling through the old workings
Pontoon drilling exists because the ground beneath the pit cannot be reached from land. QMines drills from a pontoon on the lake inside the historical open pit, and began the program on 30 July 2026, the first drilling below the pit since mining ceased in 1982. Water depths exceed 50 metres in places.
Hole 26MCDD051 shows what the drill met on the way down: timber and a void at 41.35 to 42.2 metres, semi-massive to massive sulphide to 48.9 metres with 1.5 metres of core loss and 0.65 metres of backfill, a second level of workings from 57.7 to 65.85 metres holding fill, sulphide fragments and timber, then the footwall stringer zone to the end of the hole at 94.15 metres.
The interval includes 5.1 metres of logged core loss, 0.5 metres of recovered backfill and 0.7 metres of unsampled material, all assigned zero grade. Three samples between 58.7 and 63.2 metres returned 0.25 to 0.51 per cent copper with sodium of 1.9 to 2.7 per cent, against less than 0.1 per cent in adjacent core, which QMines said is consistent with historical fill.
What is not yet known is whether the sulphide material inside the workings is in place. Its origin has not been established, and QMines said further assessment of the core, logging and historical mine plans will be required to distinguish in situ mineralisation from material displaced during historical mining.
The hole that missed the workings
The strongest support for the grade comes from a hole that never touched the old workings at all.
Hole 26MCDD054, about 32 metres north-west of 26MCDD051, was abandoned at 78.6 metres after entering a third level of workings. Its mineralisation runs over a 27.6-metre downhole section from 46.0 to 73.6 metres, broken by workings, and is reported as three separate intervals because the workings exceed the two-metre internal dilution limit. Material from within the workings was excluded, including a 3.0-metre sample of broken material weighing 0.26 kilograms, which the company said is not representative of in situ mineralisation.
Its redrill, 26MCDD054RD, collared about five metres to the north, encountered no historical workings at all, and recovered more than 95 per cent of its core from 46.5 metres. It returned 7.0 metres at 2.61 per cent copper and 0.88 grams per tonne gold from 50.0 metres to the end of the hole, including 2.0 metres at 8.62 per cent copper and 2.65 grams per tonne gold from 55.0 metres. The hole was abandoned at 57.0 metres after the casing failed, with the final metre assaying 5.39 per cent copper and 1.24 grams per tonne gold, and mineralisation open below the hole. Neither hole was surveyed downhole before abandonment.
Exploration manager Tom Bartschi said the remaining workings are not extensive, and the pontoon program is helping the company understand how much mineralisation remains in and around the workings and better define the high-grade area.
What it means for the resource
Mt Chalmers holds a Mineral Resource of 11.3 million tonnes at 0.75 per cent copper and 0.42 grams per tonne gold, estimated in March 2024 at a 0.3 per cent copper cut-off: 4.2 million tonnes Measured, 5.8 million tonnes Indicated and 1.3 million tonnes Inferred. The headline interval grades about three times the resource copper grade, and its 9.0-metre core grades more than seven times it.
The project also holds an Ore Reserve of 9.6 million tonnes at 0.65 per cent copper and 0.48 grams per tonne gold, declared in the April 2024 pre-feasibility study: 5.1 million tonnes Proved and 4.5 million tonnes Probable.
The workings are not a new problem for the estimate. Bartschi said the underground workings have been accounted for in the published Mineral Resource, which was appropriately depleted. The new results will be assessed against the existing geological model, the Mineral Resource and the available historical mine plans as part of the resource update and the Definitive Feasibility Study.
Two days before this announcement, QMines reported a step-out hole 180 metres beyond the resource returning 12 metres at 2.83 per cent copper, and said two holes were not enough to establish continuity. Drill intersections are not resources, and none of these results changes the resource estimate on their own. Mt Chalmers is a past-producing mine that yielded 1.2 million tonnes at 2.0 per cent copper, 3.6 grams per tonne gold and 19 grams per tonne silver between 1898 and 1982, and QMines owns 100 per cent of the project, 17 kilometres north-east of Rockhampton.
What happens next
Assays from a further five pontoon holes are pending, with more copper-gold results expected before Christmas. The results feed into the Mineral Resource update and the Definitive Feasibility Study, which is fully funded after QIC’s $15 million investment in April 2026. QMines said in June 2026 it was targeting completion of the study by the end of 2026.
The test for the next batch of assays is the same as for this one: whether the high grades hold up in ground without workings, and whether the resource update can turn pontoon intersections into tonnes.
This article is independent DrillTape reporting. The Stockhead article on the same results was developed in collaboration with QMines, a Stockhead advertiser at the time of publishing. DrillTape does not provide financial advice.
Sources
- QMines Limited, ASX announcement, “Exceptional 46.8m at 2.29% Copper & 1.03g/t Gold Results”, 25 November 2026. https://announcements.asx.com.au/asxpdf/20261125/pdf/077144ldjhrm6l.pdf
- Stockhead, “QMines smashes in high-grade copper hit below Mt Chalmers pit”, 25 November 2026. https://stockhead.com.au/resources/qmines-smashes-in-high-grade-copper-hit-below-mt-chalmers-pit/
- Bold Investors, “QMines Hits 46.8m of High-Grade Copper-Gold at Mt Chalmers”, 24 November 2026. https://boldinvestors.com.au/news/qmines-qml-drills-46-8m-high-grade-copper-gold-hit
- QMines Limited, quarterly activities report and Appendix 5B, quarter ended 30 September 2026, 26 October 2026 (pontoon drilling start date, program size, cash position).
- QMines Limited, ASX announcement, “High-Grade Copper Discovered 180m Beyond Mt Chalmers Resource”, 23 November 2026 (26MCDD052 step-out).
- Samso, “QMines Limited (ASX QML), Research and Coverage”, accessed 25 November 2026 (March 2024 Mineral Resource date, April 2024 PFS, DFS timetable). https://www.samso.com.au/companies/qmines-limited
- QMines, Mt Chalmers project page, accessed 25 November 2026. https://qmines.com.au/mt-chalmers/