Premium hard coking coal is up by more than a fifth this year, yet no new greenfield mine has started since 2022.
Premium hard coking coal stood at US$266 a tonne on 15 October 2026, up 22 per cent since the start of the year. A month later it was assessed at US$258.50 a tonne free on board Australia, on 17 November. The price has moved, but the supply side has not. Jameson Resources counts about US$28.5 billion in steelmaking coal deals since 2022, across 15 transactions, and not one new greenfield mine started.
The puzzle: demand has a long tail, supply has stopped growing, and the scarcest grade of all comes from a handful of places.
The price has moved first
Glencore’s average premium hard coking coal settlement price was US$236.80 a tonne for the first half of 2026, up 28 per cent on a year earlier, and its average realised steelmaking coal price rose 24 per cent, to US$206.90 a tonne. BHP’s Queensland coal business tells the same story: 18.6 million tonnes produced in the year to June 2026 at about US$210 a tonne, with steady output of 18.5 to 20.5 million tonnes guided for the year to June 2027.
Westpac, though, expects premium hard coking coal to average about US$250 a tonne in the final quarter of 2026, then moderate during 2027.
What makes premium low-vol coal different
The World Steel Association put global crude steel production at 1,849 million tonnes in 2025, with 69.4 per cent made through the blast furnace and basic oxygen route and 30.3 per cent in electric arc furnaces. In China, about 90 per cent of steel is still made in blast furnaces.
A blast furnace needs coke, and not all coking coal is equal. Premium low-volatile hard coking coal is strong, low in impurities and high in fixed carbon. Used in a furnace, less of it is needed per tonne of steel, and the furnace runs more efficiently. That gives it a price premium and an emissions advantage per tonne of steel made, and it is rare. The seaborne trade in it is dominated by two basins, the Bowen Basin in Queensland and the Elk Valley in British Columbia.
The Bowen Basin’s largest producer is the BHP Mitsubishi Alliance, a 50:50 joint venture between BHP and Mitsubishi that runs five mines and the Hay Point terminal, producing 37.3 million tonnes on a 100 per cent basis in the year to June 2026. It is the biggest premium coal producer in Queensland, but not the only one, and no miner sets the price: the benchmark is an assessed price, published by agencies such as Platts, Argus and Fastmarkets.
India is where the demand lives
The demand story is India, the world’s second largest steel producer, making 164.9 million tonnes of crude steel in 2025, up 10.4 per cent on the year. Its government aims to lift steelmaking capacity to 300 million tonnes by 2030, from about 200 million tonnes now, and to 500 million tonnes by 2047, and researchers at the University of California, Berkeley’s India Energy and Climate Center estimate that 60 to 65 per cent of the capacity planned to 2030 will use the blast furnace route.
India has almost no coking coal of its own worth using: steelmakers import about 95 per cent of it, 57.58 million tonnes in the 2024-25 financial year. In January 2026 the Indian government declared coking coal a critical and strategic mineral. India will still buy most of its premium coal abroad.
China cuts the other way: steel production there fell 4.4 per cent in 2025 to 960.8 million tonnes, and the World Steel Association expects global steel demand to be flat at 1,722 million tonnes in 2026. The long tail for coking coal is an Indian story, not a Chinese one.
The supply side has stopped building
Queensland, the largest source of seaborne steelmaking coal, is exporting less of it: S&P Global Commodity Insights base case assumptions from August 2026 put exports at 165 million tonnes a year in 2025, down from 210 million tonnes a year in 2016.
Buyers have had to purchase production rather than build it. Glencore’s purchase of a 77 per cent interest in Elk Valley Resources for US$6.93 billion in cash, completed in July 2024, is the largest of about US$28.5 billion in steelmaking coal deals since 2022. Jameson’s count: no new greenfield development has started since, the last being Olive Downs in Queensland, which began construction in April 2022.
How large the gap will be is contested. Simon Nicholas of the Institute for Energy Economics and Financial Analysis told the Coaltrans India conference in 2025 that there was growing apprehension of a deficit of about 100 million tonnes a year in the global coking coal market by 2050. The International Energy Agency, by contrast, expects global metallurgical coal demand to edge down from about 1,114 million tonnes to about 1,061 million tonnes by 2030, and Wood Mackenzie expects operating capacity to meet demand until late in its ten-year outlook.
The green steel argument is the other challenge. Researchers at UC Berkeley estimate hydrogen-based steel in India reaches about US$562 a tonne in 2030, roughly 5 per cent above steel from a new blast furnace, and becomes cheaper once rising coal prices and the European Union’s carbon border charge are counted. That is a real threat, but a 2030s one. The blast furnaces being built in India now will run for decades.
One project trying to fill the gap
If the shortage is real, the projects that can fill it are few. The most advanced is Crown Mountain, a proposed open-cut mine in British Columbia’s Elk Valley, a region with more than 60 years of premium coal production behind it.
Crown Mountain Resources holds 90 per cent of the project. Jameson Resources (ASX:JAL) owns 78.2 per cent of that company and Bathurst Resources (ASX:BRL) 21.8 per cent, giving Jameson an effective interest of about 70 per cent. The project holds 90.2 million tonnes of JORC coal resources (51.1 million tonnes measured, 15.4 million tonnes indicated, 23.7 million tonnes inferred) and a reserve of 57.5 million tonnes run of mine (43.6 million tonnes proven, 13.9 million tonnes probable), set in the July 2020 bankable feasibility study and reaffirmed in May 2025. The inferred resources date from a 2014 prefeasibility study, with no additional work since.
Over a 15-year mine life it would produce 28.5 million tonnes of saleable coal, about 1.9 million tonnes a year on average, 86 per cent hard coking coal and 14 per cent pulverised coal injection product. The strip ratio in the North and East pits is 4.1 bank cubic metres per tonne of run of mine coal in the first four years.
The May 2025 update put pre-production capital at US$394 million and cash operating costs at US$102.79 a tonne free on board Vancouver, against a long-term coal price assumption of about US$240 a tonne. Post-tax net present value was US$549 million, up from US$276 million in 2021, with an internal rate of return of 37 per cent.
The British Columbia Environmental Assessment Office issued a Section 27 notice in May 2026 confirming completion of the environmental application review. Jameson expects to submit its final revised environmental application late in 2026, starting a legislated 150-day review, with the certificate targeted for the first half of 2027 and first coal in 2029-30 after 18 to 24 months of construction.
The company has signed a consent agreement with the Yaq̓it ʔa·knuqⱡi’it First Nation, on whose unceded lands the project sits. In September and October 2026 it raised A$9.73 million, nearly double its A$5 million target, through an entitlement offer at A$0.035 a share and placements, backed by King George Investments, M Resources and the Tribeca Global Natural Resources fund. At A$0.040 a share on 9 November 2026, Jameson was capitalised at A$41.3 million.
Jameson says it is in discussions with Indian and Japanese steelmakers about offtake and equity partnerships, with letters of intent targeted for the first quarter of 2027. “It’s a coking coal story for Indian steel growth,” interim executive chairman and managing director Michael Gray said in the company’s November 2026 investor presentation.
What to watch
The next twelve months will test the shortage story: the certificate decision is targeted for the first half of 2027, and letters of intent with Asian steelmakers for the first quarter of 2027, with a final investment decision about a year after approval.
Watch the price too. If premium hard coking coal holds above US$250 a tonne, the economics of new supply improve. If it fades back towards US$200, the projects stay on the shelf and the shortage thesis gets its hardest test. The blast furnaces being built in India today will need feeding for decades. The question is who will feed them.
Disclosure: this article draws on company filings and investor presentations from Jameson Resources, Bathurst Resources, BHP, Glencore and Teck Resources. Kalkine, whose coking-coal coverage is cited in this article, discloses that its media affiliate may have received financial consideration in connection with information about certain entities covered on its website. Jameson Resources is not an advertiser of DrillTape. DrillTape provides no financial product advice.
Sources
- Jameson Resources, Investor Presentation, November 2026. https://www.marketindex.com.au/data-api/api/v1/announcements/XASX:JAL:6A1355361/pdf/inline/investor-presentation
- Jameson Resources, Quarterly Activities Report for the period ending 30 September 2026, ASX, 29 October 2026. https://announcements.asx.com.au/asxpdf/20261030/pdf/07600wd5sbxv29.pdf
- Jameson Resources, Annual Report FY2026, ASX, 30 September 2026. https://announcements.asx.com.au/asxpdf/20260930/pdf/074rv32vd77n9s.pdf
- Bathurst Resources, Update on Resources and Reserves, ASX, 30 October 2026. https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-03156194-2A1707354
- Engineering News, “Jameson confirms reserve and doubles project NPV in Crown Mountain study update”, 9 May 2025. https://www.engineeringnews.co.za/article/jameson-confirms-reserve-and-doubles-project-npv-in-crown-mountain-study-update-2025-05-09
- McKinsey Global Institute, “EAF steel: Beyond the blast furnace”, 2026. https://www.mckinsey.com/mgi/our-research/eaf-steel-beyond-the-blast-furnace
- World Steel Association, World Steel in Figures 2026, as reported November 2026. https://www.globalbrandsdrive.com/global-steel-industry/
- SteelMint, “Is the global coking coal market edging towards a supply shortfall? BigMint investigates”, February 2025. https://www.steelmint.in/is-the-global-coking-coal-market-edging-towards-a-supply-shortfall-bigmint-investigates-623537
- Wood Mackenzie, Global Metallurgical Coal 10-year Investment Horizon Outlook, 2023. https://www.woodmac.com/reports/coal-global-metallurgical-coal-10-year-investment-horizon-outlook-2023-150176696/
- India Energy and Climate Center, UC Berkeley, “The Economic Case for Green Steel Production in India”, May 2026. https://iecc.gspp.berkeley.edu/wp-content/uploads/2026/05/IECC-Economic-Case-for-Green-Steel-Production-in-India-Report-May26.pdf
- Kalkine, “Coking Coal Price 2026: Up 22% This Year at US$266 a Tonne”, October 2026. https://kalkine.com.au/news/economic-news/coking-coal-price-2026-up-22-this-year-at-us266-a-tonne-as-chinas-shortage-lifts-queensland-exports
- Argus Media, “Australia’s BHP raises coking coal output in FY2025-26”, July 2026. https://www.argusmedia.com/en/news-and-insights/latest-market-news/2852891-australia-s-bhp-raises-coking-coal-output-in-fy2025-26
- Elk Valley Coal, “Metallurgical Coal Prices Hold Strong as EVR Works to Recover Production”, November 2026. https://elkvalleycoal.com/metallurgical-coal-prices-hold-strong-as-evr-works-to-recover-production/
- SteelMint, “Global met coal prices soften; coke prices in eastern Indian rise on tight supply”, November 2026. https://www.steelmint.in/global-met-coal-prices-soften-coke-prices-in-eastern-indian-rise-on-tight-supply-808641
- Metal.com News, “India’s steel capacity expansion constrained by heavy coking coal import dependence”, November 2026. https://news.metal.com/newscontent/EYNDKDPLBQS377HBPNY6B2XHNB5BHPMNLK36JPY-indias-steel-capacity-expansion-constrained-by-heavy-coking-coal-import-dependence
- Canadian Mining Report, “Glencore Completes US$7.3 Billion Purchase of Teck’s Steelmaking Coal Business”, 2026. https://www.canadianminingreport.com/blog/glencore-s-us-7-3-billion-purchase-of-teck-s-steelmaking-coal-business-a-landmark-mining-m-a-deal-and-what-it-means-for-the-industry
- Discovery Alert, “Metallurgical Coal Companies: Why Headline Numbers Mislead”, 2026. https://discoveryalert.com/education/metallurgical-coal-companies-comparison/