Nickel Industries Limited (ASX: NIC) has received the industrial business licence its Excelsior Nickel Cobalt (ENC) plant needs to start selling refined metal. The company announced on 29 October 2026 that PT Fajar Metal Industry (FMI), the Indonesian company that owns the ENC high-pressure acid leach (HPAL) project inside the Indonesia Morowali Industrial Park, had received its industrial business licence, known as an IUI. The licence allows FMI to begin commercial sales, which the company said were expected to start in the near term.

What the licence unlocks

ENC is an integrated HPAL and refining operation, which is what makes the licence valuable. FMI can sell refined nickel and cobalt products directly, rather than selling only the intermediate MHP that most Indonesian HPAL plants produce, and so capture the full value uplift from ore to finished metal, according to the 29 October announcement.

Nickel Industries holds a 46 percent interest in ENC. The project is designed to produce MHP, nickel and cobalt sulphate and nickel cathode, and is expected to produce more than 72,000 tonnes of nickel metal a year at full capacity.

A quarter of firsts

The September 2026 quarterly report, released on 22 October 2026, recorded the commissioning milestones in sequence. Ore slurry began flowing by pipeline from the Hengjaya Mine to the ENC plant in July, and the first MHP was produced that month and delivered to the integrated refinery. The first nickel cathode followed in August and the first cobalt cathode in September.

ENC reached 50 percent of nameplate capacity during the quarter, with all three autoclaves tested independently at maximum capacity. It produced 4,840 tonnes of nickel and 494 tonnes of cobalt in MHP at a cash cost of US$13,943 per tonne of nickel, and the refinery produced 818 tonnes of nickel in cathode at a conversion cash cost of US$3,888 per tonne of nickel. ENC also received an exemption during the quarter from the Indonesian regulation introduced earlier in 2026 that restricts exports of MHP. No ENC sales were made during the quarter, while the licence was still outstanding. The company noted average prices for the quarter of about US$16,500 per tonne for LME nickel and about US$50,000 per tonne for cobalt.

The financing behind the ramp

Eight days before the licence, on 21 October 2026, FMI signed a US$245 million non-recourse project finance facility arranged and led by Oversea-Chinese Banking Corporation Limited (OCBC). The facility comprises a US$220 million amortising term loan with a seven-year tenor from first drawdown, priced at 2.00 percent a year above the Secured Overnight Financing Rate (SOFR), plus a US$25 million working capital facility. It is secured over FMI project assets and is non-recourse to Nickel Industries, and it includes an accordion feature allowing the term loan to be increased in future, potentially to US$800 million.

The 29 October announcement confirmed that all conditions precedent under the facility had been satisfied, with drawdown expected that day. Managing Director Justin Werner said the September quarter delivered “another strong, consistent quarter of EBITDA”, with group adjusted EBITDA up 4 percent to US$125.9 million.

Drought is the constraint

The ramp has a physical limit that no licence can fix. ENC output was reduced during the quarter by limited water availability after unusually severe El Nino conditions, with the Hengjaya Mine receiving only 7 millimetres of rain from the start of August to 21 October, against an average of 474 millimetres over the same period in the past ten years.

The company said full ramp-up at ENC would be delayed until the wet season, which usually starts in December, and it slightly pared back production at its rotary kiln electric furnace operations to 75 percent of capacity.

Hengjaya carries the quarter

While ENC commissioned, the Hengjaya Mine delivered its second consecutive record quarter. Ore sales rose 56 percent to 4.49 million wet metric tonnes, ore production rose 49 percent to 6.14 million wet metric tonnes, and mine adjusted EBITDA rose 68 percent to US$76.9 million. Limonite sales more than doubled and unit operating costs fell 15 percent to US$18.5 per wet metric tonne.

First commercial sales are the test

First commercial sales from ENC are the immediate test, and the December 2026 quarter report will be the first detailed look at the plant as a selling operation rather than a commissioning one. Watch sales volumes, realised cathode prices and progress back toward nameplate capacity once the wet season arrives.